Public Law 119-73 (01/23/2026)

10 U.S.C. § 8751

Notification of Navy procurement production disruptions

(a)

Requirement for Contractor To Provide Notice of Delays .—

The Secretary of the Navy shall require prime contractors of any Navy procurement program funded under either the Shipbuilding and Conversion, Navy account or the Other Procurement, Navy account to report within 15 calendar days any stop work order or other manufacturing disruption of 15 calendar days or more, by the prime contractor or any subcontractor, to the respective program manager and Navy technical authority.
(b)

Quarterly Reports .—

The Secretary of the Navy shall submit to the congressional defense committees not later than 15 calendar days after the end of each quarter of a fiscal year a report listing all notifications made pursuant to subsection (a) during the preceding quarter.

Pub. L. 116–92, div. A, title VIII, § 820(a)133 Stat. 1489Pub. L. 116–283, div. A, title XVIII, § 1878(a)134 Stat. 4292(Added , , , § 2339b; renumbered § 8751, , , .)

Editorial Notes

Prior Provisions

section 9281 of this titleA prior section 8751 was renumbered .

Amendments

Pub. L. 116–283section 2339b of this title2021— renumbered as this section.

Statutory Notes and Related Subsidiaries

Effective Date of 2021 Amendment

Pub. L. 116–283section 1801(d) of Pub. L. 116–283section 3001 of this titleAmendment by effective , with additional provisions for delayed implementation and applicability of existing law, see , set out as a note preceding .