Conditions for approval of proposed project
Environmental reviews
Request for payment by county
The Secretary concerned may request the resource advisory committee submitting a proposed project to agree to the use of project funds to pay for any environmental review, consultation, or compliance with applicable environmental laws required in connection with the project.
Conduct of environmental review
If a payment is requested under paragraph (1) and the resource advisory committee agrees to the expenditure of funds for this purpose, the Secretary concerned shall conduct environmental review, consultation, or other compliance responsibilities in accordance with Federal laws (including regulations).
Effect of refusal to pay
In general
If a resource advisory committee does not agree to the expenditure of funds under paragraph (1), the project shall be deemed withdrawn from further consideration by the Secretary concerned pursuant to this subchapter.
Effect of withdrawal
section 7127(c) of this titleA withdrawal under subparagraph (A) shall be deemed to be a rejection of the project for purposes of .
Decisions of Secretary concerned
Rejection of projects
In general
A decision by the Secretary concerned to reject a proposed project shall be at the sole discretion of the Secretary concerned.
No administrative appeal or judicial review
Notwithstanding any other provision of law, a decision by the Secretary concerned to reject a proposed project shall not be subject to administrative appeal or judicial review.
Notice of rejection
Not later than 30 days after the date on which the Secretary concerned makes the rejection decision, the Secretary concerned shall notify in writing the resource advisory committee that submitted the proposed project of the rejection and the reasons for rejection.
Notice of project approval
The Secretary concerned shall publish in the Federal Register notice of each project approved under subsection (a) if the notice would be required had the project originated with the Secretary.
Source and conduct of project
section 7123 of this titleOnce the Secretary concerned accepts a project for review under , the acceptance shall be deemed a Federal action for all purposes.
Implementation of approved projects
Cooperation
Notwithstanding chapter 63 of title 31, using project funds the Secretary concerned may enter into contracts, grants, and cooperative agreements with States and local governments, private and nonprofit entities, and landowners and other persons to assist the Secretary in carrying out an approved project.
Best value contracting
In general
For any project involving a contract authorized by paragraph (1) the Secretary concerned may elect a source for performance of the contract on a best value basis.
Factors
Requirements for project funds
Pub. L. 106–393, title II, § 204Pub. L. 110–343, div. C, title VI, § 601(a)122 Stat. 3902Pub. L. 112–141, div. F, title I, § 100101(a)(6)126 Stat. 906Pub. L. 113–40, § 10(a)(2)(B)127 Stat. 545Pub. L. 114–10, title V, § 524(c)(2)129 Stat. 180Pub. L. 115–141, div. O, title IV, § 401(b)(1)132 Stat. 1079(, as added , , ; amended , , ; , , ; , , ; , , .)
Editorial Notes
Prior Provisions
section 204 of Pub. L. 106–393section 500 of this titlePub. L. 110–343, div. C, title VI, § 601(a)122 Stat. 3893A prior was set out in a note under prior to repeal by , , .
Amendments
Pub. L. 115–1412018—Subsec. (e)(3). struck out par. (3) which established a pilot program to implement projects involving the sale of merchantable timber.
Pub. L. 114–102015—Subsec. (e)(3)(B)(iii). substituted “fiscal year 2010 and fiscal years thereafter” for “each of fiscal years 2010 through 2013”.
Pub. L. 113–402013—Subsec. (e)(3)(B)(iii). substituted “2013” for “2012”.
Pub. L. 112–1412012—Subsec. (e)(3)(B)(iii). substituted “through 2012” for “and 2011”.