42 USC CHAPTER 162, SUBCHAPTER I, Part A: Grid Infrastructure Resilience and Reliability
Result 1 of 1
   
 
42 USC CHAPTER 162, SUBCHAPTER I, Part A: Grid Infrastructure Resilience and Reliability
From Title 42—THE PUBLIC HEALTH AND WELFARECHAPTER 162—ENERGY INFRASTRUCTURESUBCHAPTER I—GRID INFRASTRUCTURE AND RESILIENCY

Part A—Grid Infrastructure Resilience and Reliability

§18711. Preventing outages and enhancing the resilience of the electric grid

(a) Definitions

In this section:

(1) Disruptive event

The term "disruptive event" means an event in which operations of the electric grid are disrupted, preventively shut off, or cannot operate safely due to extreme weather, wildfire, or a natural disaster.

(2) Eligible entity

The term "eligible entity" means—

(A) an electric grid operator;

(B) an electricity storage operator;

(C) an electricity generator;

(D) a transmission owner or operator;

(E) a distribution provider;

(F) a fuel supplier; and

(G) any other relevant entity, as determined by the Secretary.

(3) Natural disaster

The term "natural disaster" has the meaning given the term in section 5195a(a) of this title.

(4) Power line

The term "power line" includes a transmission line or a distribution line, as applicable.

(5) Program

The term "program" means the program established under subsection (b).

(b) Establishment of program

Not later than 180 days after November 15, 2021, the Secretary shall establish a program under which the Secretary shall make grants to eligible entities, States, and Indian Tribes in accordance with this section.

(c) Grants to eligible entities

(1) In general

The Secretary may make a grant under the program to an eligible entity to carry out activities that—

(A) are supplemental to existing hardening efforts of the eligible entity planned for any given year; and

(B)(i) reduce the risk of any power lines owned or operated by the eligible entity causing a wildfire; or

(ii) increase the ability of the eligible entity to reduce the likelihood and consequences of disruptive events.

(2) Application

(A) In general

An eligible entity desiring a grant under the program shall submit to the Secretary an application at such time, in such manner, and containing such information as the Secretary may require.

(B) Requirement

As a condition of receiving a grant under the program, an eligible entity shall submit to the Secretary, as part of the application of the eligible entity submitted under subparagraph (A), a report detailing past, current, and future efforts by the eligible entity to reduce the likelihood and consequences of disruptive events.

(3) Limitation

The Secretary may not award a grant to an eligible entity in an amount that is greater than the total amount that the eligible entity has spent in the previous 3 years on efforts to reduce the likelihood and consequences of disruptive events.

(4) Priority

In making grants to eligible entities under the program, the Secretary shall give priority to projects that, in the determination of the Secretary, will generate the greatest community benefit (whether rural or urban) in reducing the likelihood and consequences of disruptive events.

(5) Small utilities set aside

The Secretary shall ensure that not less than 30 percent of the amounts made available to eligible entities under the program are made available to eligible entities that sell not more than 4,000,000 megawatt hours of electricity per year.

(d) Grants to States and Indian Tribes

(1) In general

The Secretary, in accordance with this subsection, may make grants under the program to States and Indian Tribes, which each State or Indian Tribe may use to award grants to eligible entities.

(2) Annual application

(A) In general

For each fiscal year, to be eligible to receive a grant under this subsection, a State or Indian Tribe shall submit to the Secretary an application that includes a plan described in subparagraph (B).

(B) Plan required

A plan prepared by a State or Indian Tribe for purposes of an application described in subparagraph (A) shall—

(i) describe the criteria and methods that will be used by the State or Indian Tribe to award grants to eligible entities;

(ii) be adopted after notice and a public hearing; and

(iii) describe the proposed funding distributions and recipients of the grants to be provided by the State or Indian Tribe.

(3) Distribution of funds

(A) In general

The Secretary shall provide grants to States and Indian Tribes under this subsection based on a formula determined by the Secretary, in accordance with subparagraph (B).

(B) Requirement

The formula referred to in subparagraph (A) shall be based on the following factors:

(i) The total population of the State or Indian Tribe.

(ii)(I) The total area of the State or the land of the Indian Tribe; or

(II) the areas in the State or on the land of the Indian Tribe with a low ratio of electricity customers per mileage of power lines.

(iii) The probability of disruptive events in the State or on the land of the Indian Tribe during the previous 10 years, as determined based on the number of federally declared disasters or emergencies in the State or on the land of the Indian Tribe, as applicable, including—

(I) disasters for which Fire Management Assistance Grants are provided under section 5187 of this title;

(II) major disasters declared by the President under section 5170 of this title;

(III) emergencies declared by the President under section 5191 of this title; and

(IV) any other federally declared disaster or emergency in the State or on the land of the Indian Tribe.


(iv) The number and severity, measured by population and economic impacts, of disruptive events experienced by the State or Indian Tribe on or after January 1, 2011.

(v) The total amount, on a per capita basis, of public and private expenditures during the previous 10 years to carry out mitigation efforts to reduce the likelihood and consequences of disruptive events in the State or on the land of the Indian Tribe, with States or Indian Tribes with higher per capita expenditures receiving additional weight or consideration as compared to States or Indian Tribes with lower per capita expenditures.

(C) Annual update of data used in distribution of funds

Beginning 1 year after November 15, 2021, the Secretary shall annually update—

(i) all data relating to the factors described in subparagraph (B); and

(ii) all other data used in distributing grants to States and Indian Tribes under this subsection.

(4) Oversight

The Secretary shall ensure that each grant provided to a State or Indian Tribe under the program is allocated, pursuant to the applicable plan of the State or Indian Tribe, to eligible entities for projects within the State or on the land of the Indian Tribe.

(5) Priority

In making grants to eligible entities using funds made available to the applicable State or Indian Tribe under the program, the State or Indian Tribe shall give priority to projects that, in the determination of the State or Indian Tribe, will generate the greatest community benefit (whether rural or urban) in reducing the likelihood and consequences of disruptive events.

(6) Small utilities set aside

A State or Indian Tribe receiving a grant under the program shall ensure that, of the amounts made available to eligible entities from funds made available to the State or Indian Tribe under the program, the percentage made available to eligible entities that sell not more than 4,000,000 megawatt hours of electricity per year is not less than the percentage of all customers in the State or Indian Tribe that are served by those eligible entities.

(7) Technical assistance and administrative expenses

Of the amounts made available to a State or Indian Tribe under the program each fiscal year, the State or Indian Tribe may use not more than 5 percent for—

(A) providing technical assistance under subsection (g)(1)(A); and

(B) administrative expenses associated with the program.

(8) Matching requirement

Each State and Indian Tribe shall be required to match 15 percent of the amount of each grant provided to the State or Indian Tribe under the program.

(e) Use of grants

(1) In general

A grant awarded to an eligible entity under the program may be used for activities, technologies, equipment, and hardening measures to reduce the likelihood and consequences of disruptive events, including—

(A) weatherization technologies and equipment;

(B) fire-resistant technologies and fire prevention systems;

(C) monitoring and control technologies;

(D) the undergrounding of electrical equipment;

(E) utility pole management;

(F) the relocation of power lines or the reconductoring of power lines with low-sag, advanced conductors;

(G) vegetation and fuel-load management;

(H) the use or construction of distributed energy resources for enhancing system adaptive capacity during disruptive events, including—

(i) microgrids; and

(ii) battery-storage subcomponents;


(I) adaptive protection technologies;

(J) advanced modeling technologies;

(K) hardening of power lines, facilities, substations, of 1 other systems; and

(L) the replacement of old overhead conductors and underground cables.

(2) Prohibitions and limitations

(A) In general

A grant awarded to an eligible entity under the program may not be used for—

(i) construction of a new—

(I) electric generating facility; or

(II) large-scale battery-storage facility that is not used for enhancing system adaptive capacity during disruptive events; or


(ii) cybersecurity.

(B) Certain investments eligible for recovery

(i) In general

An eligible entity may not seek cost recovery for the portion of the cost of any system, technology, or equipment that is funded through a grant awarded under the program.

(ii) Savings provision

Nothing in this subparagraph prohibits an eligible entity from recovering through traditional or incentive-based ratemaking any portion of an investment in a system, technology, or equipment that is not funded by a grant awarded under the program.

(C) Application limitations

An eligible entity may not submit an application for a grant provided by the Secretary under subsection (c) and a grant provided by a State or Indian Tribe pursuant to subsection (d) during the same application cycle.

(f) Distribution of funding

Of the amounts made available to carry out the program for a fiscal year, the Secretary shall ensure that—

(1) 50 percent is used to award grants to eligible entities under subsection (c); and

(2) 50 percent is used to make grants to States and Indian Tribes under subsection (d).

(g) Technical and other assistance

(1) In general

The Secretary, States, and Indian Tribes may—

(A) provide technical assistance and facilitate the distribution and sharing of information to reduce the likelihood and consequences of disruptive events; and

(B) promulgate consumer-facing information and resources to inform the public of best practices and resources relating to reducing the likelihood and consequences of disruptive events.

(2) Use of funds by the Secretary

Of the amounts made available to the Secretary to carry out the program each fiscal year, the Secretary may use not more than 5 percent for—

(A) providing technical assistance under paragraph (1)(A); and

(B) administrative expenses associated with the program.

(h) Matching requirement

(1) In general

Except as provided in paragraph (2), an eligible entity that receives a grant under this section shall be required to match 100 percent of the amount of the grant.

(2) Exception for small utilities

An eligible entity that sells not more than 4,000,000 megawatt hours of electricity per year shall be required to match 1/3 of the amount of the grant.

(i) Biennial report to Congress

(1) In general

Not later than 2 years after November 15, 2021, and every 2 years thereafter through 2026, the Secretary shall submit to the Committee on Energy and Natural Resources of the Senate and the Committee on Energy and Commerce of the House of Representatives a report describing the program.

(2) Requirements

The report under paragraph (1) shall include information and data on—

(A) the costs of the projects for which grants are awarded to eligible entities;

(B) the types of activities, technologies, equipment, and hardening measures funded by those grants; and

(C) the extent to which the ability of the power grid to withstand disruptive events has increased.

(j) Authorization of appropriations

There is authorized to be appropriated to the Secretary to carry out the program $5,000,000,000 for the period of fiscal years 2022 through 2026.

(Pub. L. 117–58, div. D, title I, §40101, Nov. 15, 2021, 135 Stat. 923.)


Statutory Notes and Related Subsidiaries

Wage Rate Requirements

For provisions relating to rates of wages to be paid to laborers and mechanics on projects for construction, alteration, or repair work funded under div. D or an amendment by div. D of Pub. L. 117–58, including authority of Secretary of Labor, see section 18851 of this title.

1 So in original.

§18712. Electric grid reliability and resilience research, development, and demonstration

(a) Definition of Federal financial assistance

In this section, the term "Federal financial assistance" has the meaning given the term in section 200.1 of title 2, Code of Federal Regulations.

(b) Energy infrastructure Federal financial assistance program

(1) Definitions

In this subsection:

(A) Eligible entity

The term "eligible entity" means each of—

(i) a State;

(ii) a combination of 2 or more States;

(iii) an Indian Tribe;

(iv) a unit of local government; and

(v) a public utility commission.

(B) Program

The term "program" means the competitive Federal financial assistance program established under paragraph (2).

(2) Establishment

Not later than 180 days after November 15, 2021, the Secretary shall establish a program, to be known as the "Program Upgrading Our Electric Grid and Ensuring Reliability and Resiliency", to provide, on a competitive basis, Federal financial assistance to eligible entities to carry out the purpose described in paragraph (3).

(3) Purpose

The purpose of the program is to coordinate and collaborate with electric sector owners and operators—

(A) to demonstrate innovative approaches to transmission, storage, and distribution infrastructure to harden and enhance resilience and reliability; and

(B) to demonstrate new approaches to enhance regional grid resilience, implemented through States by public and rural electric cooperative entities on a cost-shared basis.

(4) Applications

To be eligible to receive Federal financial assistance under the program, an eligible entity shall submit to the Secretary an application at such time, in such manner, and containing such information as the Secretary may require, including a description of—

(A) how the Federal financial assistance would be used;

(B) the expected beneficiaries, and

(C) in the case of a proposal from an eligible entity described in paragraph (1)(A)(ii), how the proposal would improve regional energy infrastructure.

(5) Selection

The Secretary shall select eligible entities to receive Federal financial assistance under the program on a competitive basis.

(6) Cost share

Section 16352 of this title shall apply to Federal financial assistance provided under the program.

(7) Authorization of appropriations

There is authorized to be appropriated to the Secretary to carry out this subsection, $5,000,000,000 for the period of fiscal years 2022 through 2026.

(c) Energy improvement in rural or remote areas

(1) Definition of rural or remote area

In this subsection, the term "rural or remote area" means a city, town, or unincorporated area that has a population of not more than 10,000 inhabitants.

(2) Required activities

The Secretary shall carry out activities to improve in rural or remote areas of the United States—

(A) the resilience, safety, reliability, and availability of energy; and

(B) environmental protection from adverse impacts of energy generation.

(3) Federal financial assistance

The Secretary, in consultation with the Secretary of the Interior, may provide Federal financial assistance to rural or remote areas for the purpose of—

(A) overall cost-effectiveness of energy generation, transmission, or distribution systems;

(B) siting or upgrading transmission and distribution lines;

(C) reducing greenhouse gas emissions from energy generation by rural or remote areas;

(D) providing or modernizing electric generation facilities;

(E) developing microgrids; and

(F) increasing energy efficiency.

(4) Authorization of appropriations

There is authorized to be appropriated to the Secretary to carry out this subsection, $1,000,000,000 for the period of fiscal years 2022 through 2026.

(d) Energy infrastructure resilience framework

(1) In general

The Secretary, in collaboration with the Secretary of Homeland Security, the Federal Energy Regulatory Commission, the North American Electric Reliability Corporation, and interested energy infrastructure stakeholders, shall develop common analytical frameworks, tools, metrics, and data to assess the resilience, reliability, safety, and security of energy infrastructure in the United States, including by developing and storing an inventory of easily transported high-voltage recovery transformers and other required equipment.

(2) Assessment and report

(A) Assessment

The Secretary shall carry out an assessment of—

(i) with respect to the inventory of high-voltage recovery transformers, new transformers, and other equipment proposed to be developed and stored under paragraph (1)—

(I) the policies, technical specifications, and logistical and program structures necessary to mitigate the risks associated with the loss of high-voltage recovery transformers;

(II) the technical specifications for high-voltage recovery transformers;

(III) where inventory of high-voltage recovery transformers should be stored;

(IV) the quantity of high-voltage recovery transformers necessary for the inventory;

(V) how the stored inventory of high-voltage recovery transformers would be secured and maintained;

(VI) how the high-voltage recovery transformers may be transported;

(VII) opportunities for developing new flexible advanced transformer designs; and

(VIII) whether new Federal regulations or cost-sharing requirements are necessary to carry out the storage of high-voltage recovery transformers; and


(ii) any efforts carried out by industry as of the date of the assessment—

(I) to share transformers and equipment;

(II) to develop plans for next generation transformers; and

(III) to plan for surge and long-term manufacturing of, and long-term standardization of, transformer designs.

(B) Protection of information

Information that is provided to, generated by, or collected by the Secretary under subparagraph (A) shall be considered to be critical electric infrastructure information under section 824o–1 of title 16.

(C) Report

Not later than 180 days after November 15, 2021, the Secretary shall submit to Congress a report describing the results of the assessment carried out under subparagraph (A).

(Pub. L. 117–58, div. D, title I, §40103, Nov. 15, 2021, 135 Stat. 928.)


Statutory Notes and Related Subsidiaries

Wage Rate Requirements

For provisions relating to rates of wages to be paid to laborers and mechanics on projects for construction, alteration, or repair work funded under div. D or an amendment by div. D of Pub. L. 117–58, including authority of Secretary of Labor, see section 18851 of this title.

§18713. Transmission facilitation program

(a) Definitions

In this section:

(1) Capacity contract

The term "capacity contract" means a contract entered into by the Secretary and an eligible entity under subsection (e)(1)(A) for the right to the use of the transmission capacity of an eligible project.

(2) Eligible electric power transmission line

The term "eligible electric power transmission line" means an electric power transmission line that is capable of transmitting not less than—

(A) 1,000 megawatts; or

(B) in the case of a project that consists of upgrading an existing transmission line or constructing a new transmission line in an existing transmission, transportation, or telecommunications infrastructure corridor, 500 megawatts.

(3) Eligible entity

The term "eligible entity" means an entity seeking to carry out an eligible project.

(4) Eligible project

The term "eligible project" means a project (including any related facility)—

(A) to construct a new or replace an existing eligible electric power transmission line;

(B) to increase the transmission capacity of an existing eligible electric power transmission line; or

(C) to connect an isolated microgrid to an existing transmission, transportation, or telecommunications infrastructure corridor located in Alaska, Hawaii, or a territory of the United States.

(5) Fund

The term "Fund" means the Transmission Facilitation Fund established by subsection (d)(1).

(6) Program

The term "program" means the Transmission Facilitation Program established by subsection (b).

(7) Related facility

(A) In general

The term "related facility" means a facility related to an eligible project described in paragraph (4).

(B) Exclusions

The term "related facility" does not include—

(i) facilities used primarily to generate electric energy; or

(ii) facilities used in the local distribution of electric energy.

(b) Establishment

There is established a program, to be known as the "Transmission Facilitation Program", under which the Secretary shall facilitate the construction of electric power transmission lines and related facilities in accordance with subsection (e).

(c) Applications

(1) In general

To be eligible for assistance under this section, an eligible entity shall submit to the Secretary an application at such time, in such manner, and containing such information as the Secretary may require.

(2) Procedures

The Secretary shall establish procedures for the solicitation and review of applications from eligible entities.

(d) Funding

(1) Transmission Facilitation Fund

There is established in the Treasury a fund, to be known as the "Transmission Facilitation Fund", consisting of—

(A) all amounts received by the Secretary, including receipts, collections, and recoveries, from any source relating to expenses incurred by the Secretary in carrying out the program, including—

(i) costs recovered pursuant to paragraph (4);

(ii) amounts received as repayment of a loan issued to an eligible entity under subsection (e)(1)(B); and

(iii) amounts contributed by eligible entities for the purpose of carrying out an eligible project with respect to which the Secretary is participating with the eligible entity under subsection (e)(1)(C);


(B) all amounts borrowed from the Secretary of the Treasury by the Secretary for the program under paragraph (2); and

(C) any amounts appropriated to the Secretary for the program.

(2) Borrowing authority

The Secretary of the Treasury may, without further appropriation and without fiscal year limitation, loan to the Secretary on such terms as may be fixed by the Secretary and the Secretary of the Treasury, such sums as, in the judgment of the Secretary, are from time to time required for the purpose of carrying out the program, not to exceed, in the aggregate (including deferred interest), $2,500,000,000 in outstanding repayable balances at any 1 time.

(3) Authorization of appropriations

There is authorized to be appropriated to the Secretary to carry out the program, including for any administrative expenses of carrying out the program that are not recovered under paragraph (4), $10,000,000 for each of fiscal years 2022 through 2026.

(4) Cost recovery

(A) In general

Except as provided in subparagraph (B), the cost of any facilitation activities carried out by the Secretary under subsection (e)(1) shall be collected—

(i) from eligible entities receiving the benefit of the applicable facilitation activity, on a schedule to be determined by the Secretary; or

(ii) with respect to a contracted transmission capacity under subsection (e)(1)(A) through rates charged for the use of the contracted transmission capacity.

(B) Forgiveness of balances

(i) Termination or end of useful life

If, at the end of the useful life of an eligible project or the termination of a capacity contract under subsection (f)(5), there is a remaining balance owed to the Treasury under this section, the balance shall be forgiven.

(ii) Unconstructed projects

Funds expended to study projects that are considered pursuant to this section but that are not constructed shall be forgiven.

(C) Recovery of costs of eligible projects

The Secretary may collect the costs of any activities carried out by the Secretary with respect to an eligible project in which the Secretary participates with an eligible entity under subsection (e)(1)(C) through rates charged to customers benefitting from the new transmission capability provided by the eligible project.

(e) Facilitation of eligible projects

(1) In general

To facilitate eligible projects, the Secretary may—

(A) subject to subsections (f) and (i), enter into a capacity contract with respect to an eligible project prior to the date on which the eligible project is completed;

(B) subject to subsections (g) and (i), issue a loan to an eligible entity for the costs of carrying out an eligible project; or

(C) subject to subsections (h) and (i), participate with an eligible entity in designing, developing, constructing, operating, maintaining, or owning an eligible project.

(2) Requirement

The provision and receipt of assistance for an eligible project under paragraph (1) shall be subject to such terms and conditions as the Secretary determines to be appropriate—

(A) to ensure the success of the program; and

(B) to protect the interests of the United States.

(f) Capacity contracts

(1) Purpose

In entering into capacity contracts under subsection (e)(1)(A), the Secretary shall seek to enter into capacity contracts that will encourage other entities to enter into contracts for the transmission capacity of the eligible project.

(2) Payment

The amount paid by the Secretary to an eligible entity under a capacity contract for the right to the use of the transmission capacity of an eligible project shall be—

(A) the fair market value for the use of the transmission capacity, as determined by the Secretary, taking into account, as the Secretary determines to be necessary, the comparable value for the use of the transmission capacity of other electric power transmission lines; and

(B) on a schedule and in such divided amounts, which may be a single amount, that the Secretary determines are likely to facilitate construction of the eligible project, taking into account standard industry practice and factors specific to each applicant, including, as applicable—

(i) potential review by a State regulatory entity of the revenue requirement of an electric utility; and

(ii) the financial model of an independent transmission developer.

(3) Limitations

A capacity contract shall—

(A) be for a term of not more than 40 years; and

(B) be for not more than 50 percent of the total proposed transmission capacity of the applicable eligible project.

(4) Transmission marketing

(A) In general

If the Secretary has not terminated a capacity contract under paragraph (5) before the applicable eligible project enters into service, the Secretary may enter into 1 or more contracts with a third party to market the transmission capacity of the eligible project to which the Secretary holds rights under the capacity contract.

(B) Return

Subject to subparagraph (D), the Secretary shall seek to ensure that any contract entered into under subparagraph (A) maximizes the financial return to the Federal Government.

(C) Competitive solicitation

The Secretary shall only select third parties for contracts under this paragraph through a competitive solicitation.

(D) Requirement

The marketing of capacity pursuant to this subsection, including any marketing by a third party under subparagraph (A), shall be undertaken consistent with the requirements of the Federal Power Act (16 U.S.C. 791a et seq.).

(5) Termination

(A) In general

The Secretary shall seek to terminate a capacity contract as soon as practicable after determining that sufficient transmission capacity of the eligible project has been secured by other entities to ensure the long-term financial viability of the eligible project, including through 1 or more transfers under subparagraph (B).

(B) Transfer

On payment to the Secretary by a third party for transmission capacity to which the Secretary has rights under a capacity contract, the Secretary may transfer the rights to that transmission capacity to that third party.

(C) Relinquishment

On payment to the Secretary by the applicable eligible entity for transmission capacity to which the Secretary has rights under a capacity contract, the Secretary may relinquish the rights to that transmission capacity to the eligible entity.

(D) Requirement

A payment under subparagraph (B) or (C) shall be in an amount sufficient for the Secretary to recover any remaining costs incurred by the Secretary with respect to the quantity of transmission capacity affected by the transfer under subparagraph (B) or the relinquishment under subparagraph (C), as applicable.

(6) Other Federal capacity positions

The existence of a capacity contract does not preclude a Federal entity, including a Federal power marketing administration, from otherwise securing transmission capacity at any time from an eligible project, to the extent that the Federal entity is authorized to secure that transmission capacity.

(7) Form of financial assistance

Entering into a capacity contract under subsection (e)(1)(A) shall be considered a form of financial assistance described in section 1508.1(q)(1)(vii) of title 40, Code of Federal Regulations (as in effect on November 15, 2021).

(8) Transmission planning region consultation

Prior to entering into a capacity contract under this subsection, the Secretary shall consult with the relevant transmission planning region regarding the transmission planning region's identification of needs, and the Secretary shall minimize, to the extent possible, duplication or conflict with the transmission planning region's needs determination and selection of projects that meet such needs.

(g) Interest rate on loans

The rate of interest to be charged in connection with any loan made by the Secretary to an eligible entity under subsection (e)(1)(B) shall be fixed by the Secretary, taking into consideration market yields on outstanding marketable obligations of the United States of comparable maturities as of the date of the loan.

(h) Public-private partnerships

The Secretary may participate with an eligible entity with respect to an eligible project under subsection (e)(1)(C) if the Secretary determines that the eligible project—

(1)(A) is located in an area designated as a national interest electric transmission corridor pursuant to section 216(a) of the Federal Power Act [16 U.S.C. 824p(a)]; or

(B) is necessary to accommodate an actual or projected increase in demand for electric transmission capacity across more than 1 State or transmission planning region;

(2) is consistent with efficient and reliable operation of the transmission grid;

(3) will be operated in conformance with prudent utility practices;

(4) will be operated in conformance with the rules of—

(A) a Transmission Organization (as defined in section 3 of the Federal Power Act (16 U.S.C. 796)), if applicable; or

(B) a regional reliability organization; and


(5) is not duplicative of the functions of existing transmission facilities that are the subject of ongoing siting and related permitting proceedings.

(i) Certification

Prior to taking action to facilitate an eligible project under subparagraph (A), (B), or (C) of subsection (e)(1), the Secretary shall certify that—

(1) the eligible project is in the public interest;

(2) the eligible project is unlikely to be constructed in as timely a manner or with as much transmission capacity in the absence of facilitation under this section, including with respect to an eligible project for which a Federal investment tax credit may be allowed; and

(3) it is reasonable to expect that the proceeds from the eligible project will be adequate, as applicable—

(A) to recover the cost of a capacity contract entered into under subsection (e)(1)(A);

(B) to repay a loan provided under subsection (e)(1)(B); or

(C) to repay any amounts borrowed from the Secretary of the Treasury under subsection (d)(2).

(j) Other authorities, limitations, and effects

(1) Participation

The Secretary may permit other entities to participate in the financing, construction, and ownership of eligible projects facilitated under this section.

(2) Operations and maintenance

Facilitation by the Secretary of an eligible project under this section does not create any obligation on the part of the Secretary to operate or maintain the eligible project.

(3) Federal facilities

For purposes of cost recovery under subsection (d)(4) and repayment of a loan issued under subsection (e)(1)(B), each eligible project facilitated by the Secretary under this section shall be treated as separate and distinct from—

(A) each other eligible project; and

(B) all other Federal power and transmission facilities.

(4) Effect on ancillary services authority and obligations

Nothing in this section confers on the Secretary or any Federal power marketing administration any additional authority or obligation to provide ancillary services to users of transmission facilities constructed or upgraded under this section.

(5) Effect on Western Area Power Administration projects

Nothing in this section affects—

(A) any pending project application before the Western Area Power Administration under section 16421a of this title; or

(B) any agreement entered into by the Western Power Administration under that section.

(6) Third-party finance

Nothing in this section precludes an eligible project facilitated under this section from being eligible as a project under section 16421 of this title.

(7) Limitation on loans

An eligible project may not be the subject of both—

(A) a loan under subsection (e)(1)(B); and

(B) a Federal loan under section 16421a of this title.

(8) Considerations

In evaluating eligible projects for possible facilitation under this section, the Secretary shall prioritize projects that, to the maximum extent practicable—

(A) use technology that enhances the capacity, efficiency, resiliency, or reliability of an electric power transmission system, including—

(i) reconductoring of an existing electric power transmission line with advanced conductors; and

(ii) hardware or software that enables dynamic line ratings, advanced power flow control, or grid topology optimization;


(B) will improve the resiliency and reliability of an electric power transmission system;

(C) facilitate interregional transfer capacity that supports strong and equitable economic growth; and

(D) contribute to national or subnational goals to lower electricity sector greenhouse gas emissions.

(Pub. L. 117–58, div. D, title I, §40106, Nov. 15, 2021, 135 Stat. 934.)


Editorial Notes

References in Text

The Federal Power Act, referred to in subsec. (f)(4)(D), is act June 10, 1920, ch. 285, 41 Stat. 1063, which is classified generally to chapter 12 (§791a et seq.) of Title 16, Conservation. For complete classification of this Act to the Code, see section 791a of Title 16 and Tables.


Statutory Notes and Related Subsidiaries

Wage Rate Requirements

For provisions relating to rates of wages to be paid to laborers and mechanics on projects for construction, alteration, or repair work funded under div. D or an amendment by div. D of Pub. L. 117–58, including authority of Secretary of Labor, see section 18851 of this title.