Submission; contractual nature of approval by Administrator; agreement on eligible costs; single grant
Agreement on eligible costs.—
Limitation on modifications .—
Limitation on effect .—
Periodic payments
The Administrator shall, from time to time as the work progresses, make payments to the recipient of a grant for costs of construction incurred on a project. These payments shall at no time exceed the Federal share of the cost of construction incurred to the date of the voucher covering such payment plus the Federal share of the value of the materials which have been stockpiled in the vicinity of such construction in conformity to plans and specifications for the project.
Final payments
After completion of a project and approval of the final voucher by the Administrator, he shall pay out of the appropriate sums the unpaid balance of the Federal share payable on account of such project.
Projects eligible
Nothing in this chapter shall be construed to require, or to authorize the Administrator to require, that grants under this chapter for construction of treatment works be made only for projects which are operable units usable for sewage collection, transportation, storage, waste treatment, or for similar purposes without additional construction.
Technical and legal assistance in administration and enforcement of contracts; intervention in civil actions
At the request of a grantee under this subchapter, the Administrator is authorized to provide technical and legal assistance in the administration and enforcement of any contract in connection with treatment works assisted under this subchapter, and to intervene in any civil action involving the enforcement of such a contract.
Design/build projects
Agreement
Consistent with State law, an applicant who proposes to construct waste water treatment works may enter into an agreement with the Administrator under this subsection providing for the preparation of construction plans and specifications and the erection of such treatment works, in lieu of proceeding under the other provisions of this section.
Limitation on projects
Required terms
Limitation on application
Subsections (a), (b), and (c) of this section shall not apply to grants made pursuant to this subsection.
Reservation to assure compliance
The Administrator shall reserve a portion of the grant to assure contract compliance until final project approval as defined by the Administrator. If the amount agreed to under paragraph (3)(A) exceeds the cost of designing and constructing the treatment works, the Administrator shall reallot the amount of the excess to the State in which such treatment works are located for the fiscal year in which such audit is completed.
Limitation on obligations
section 1285 of this titleThe Administrator shall not obligate more than 20 percent of the amount allotted to a State for a fiscal year under for grants pursuant to this subsection.
Allowance
lThe Administrator shall determine an allowance for facilities planning for projects constructed under this subsection in accordance with section 1281() of this title.
Limitation on Federal contributions
In no event shall the Federal contribution for the cost of preparing construction plans and specifications and the building and erection of treatment works pursuant to this subsection exceed the amount agreed upon under paragraph (3).
Recovery action
In any case in which the recipient of a grant made pursuant to this subsection does not comply with the terms of the agreement entered into under paragraph (3), the Administrator is authorized to take such action as may be necessary to recover the amount of the Federal contribution to the project.
Prevention of double benefits
A recipient of a grant made pursuant to this subsection shall not be eligible for any other grants under this subchapter for the same project.
June 30, 1948, ch. 758Pub. L. 92–500, § 286 Stat. 835Pub. L. 93–243, § 287 Stat. 1069Pub. L. 95–21791 Stat. 1571Pub. L. 96–483, § 694 Stat. 2362Pub. L. 97–117, § 995 Stat. 1626Pub. L. 100–4, title II101 Stat. 16(, title II, § 203, as added , , ; amended , , ; , §§ 18, 19, , , 1572; , , ; , , ; , §§ 203, 204, , , 17.)
Editorial Notes
Amendments
Pub. L. 100–4, § 2031987—Subsec. (a). , designated provision relating to submission of plans, specifications, and estimates, and provision relating to contractual nature of approval by Administrator as par. (1), designated provision relating to requirements for awarding single grant for combined Federal share of cost of preparing plans and specifications, and building and erection of treatment works as par. (3), and added par. (2).
Pub. L. 100–4, § 204Subsec. (f). , added subsec. (f).
Pub. L. 97–1171981—Subsec. (a). substituted “$8,000,000” for “$4,000,000” and struck out provision that, if any State is found by the Administrator to have unusually high costs of construction, the Administrator may authorize a single grant where the estimated total cost of the treatment works does not exceed $5,000,000.
Pub. L. 96–4831980—Subsec. (a). substituted “$4,000,000” and “$5,000,000” for “$2,000,000” and “$3,000,000”, respectively.
Pub. L. 95–217, § 181977—Subsec. (a). , provided that, in the case of a treatment works that has an estimated total cost of $2,000,000 or less (as determined by the Administrator), and the population of the applicant municipality is twenty-five thousand or less (according to the most recent United States census), upon completion of an approved facility plan, a single grant may be awarded for the combined Federal share of the cost of preparing construction plans and specifications, and the building and erection of the treatment works, and that, if any State is found by the Administrator to have unusually high costs of construction, the Administrator may authorize a single grant where the estimated total cost of the treatment works does not exceed $3,000,000.
Pub. L. 95–217, § 19Subsec. (e). , added subsec. (e).
Pub. L. 93–2431974—Subsec. (d). added subsec. (d).