Unjust or preferential rates, etc.; statement of reasons for changes; hearing; specification of issues
Whenever the Commission, after a hearing held upon its own motion or upon complaint, shall find that any rate, charge, or classification, demanded, observed, charged, or collected by any public utility for any transmission or sale subject to the jurisdiction of the Commission, or that any rule, regulation, practice, or contract affecting such rate, charge, or classification is unjust, unreasonable, unduly discriminatory or preferential, the Commission shall determine the just and reasonable rate, charge, classification, rule, regulation, practice, or contract to be thereafter observed and in force, and shall fix the same by order. Any complaint or motion of the Commission to initiate a proceeding under this section shall state the change or changes to be made in the rate, charge, classification, rule, regulation, practice, or contract then in force, and the reasons for any proposed change or changes therein. If, after review of any motion or complaint and answer, the Commission shall decide to hold a hearing, it shall fix by order the time and place of such hearing and shall specify the issues to be adjudicated.
Refund effective date; preferential proceedings; statement of reasons for delay; burden of proof; scope of refund order; refund orders in cases of dilatory behavior; interest
section 824d of this titleProvidedWhenever the Commission institutes a proceeding under this section, the Commission shall establish a refund effective date. In the case of a proceeding instituted on complaint, the refund effective date shall not be earlier than the date of the filing of such complaint nor later than 5 months after the filing of such complaint. In the case of a proceeding instituted by the Commission on its own motion, the refund effective date shall not be earlier than the date of the publication by the Commission of notice of its intention to initiate such proceeding nor later than 5 months after the publication date. Upon institution of a proceeding under this section, the Commission shall give to the decision of such proceeding the same preference as provided under and otherwise act as speedily as possible. If no final decision is rendered by the conclusion of the 180-day period commencing upon initiation of a proceeding pursuant to this section, the Commission shall state the reasons why it has failed to do so and shall state its best estimate as to when it reasonably expects to make such decision. In any proceeding under this section, the burden of proof to show that any rate, charge, classification, rule, regulation, practice, or contract is unjust, unreasonable, unduly discriminatory, or preferential shall be upon the Commission or the complainant. At the conclusion of any proceeding under this section, the Commission may order refunds of any amounts paid, for the period subsequent to the refund effective date through a date fifteen months after such refund effective date, in excess of those which would have been paid under the just and reasonable rate, charge, classification, rule, regulation, practice, or contract which the Commission orders to be thereafter observed and in force: , That if the proceeding is not concluded within fifteen months after the refund effective date and if the Commission determines at the conclusion of the proceeding that the proceeding was not resolved within the fifteen-month period primarily because of dilatory behavior by the public utility, the Commission may order refunds of any or all amounts paid for the period subsequent to the refund effective date and prior to the conclusion of the proceeding. The refunds shall be made, with interest, to those persons who have paid those rates or charges which are the subject of the proceeding.
Refund considerations; shifting costs; reduction in revenues; “electric utility companies” and “registered holding company” defined
Provided1
Investigation of costs
The Commission upon its own motion, or upon the request of any State commission whenever it can do so without prejudice to the efficient and proper conduct of its affairs, may investigate and determine the cost of the production or transmission of electric energy by means of facilities under the jurisdiction of the Commission in cases where the Commission has no authority to establish a rate governing the sale of such energy.
Short-term sales
June 10, 1920, ch. 285Aug. 26, 1935, ch. 68749 Stat. 852Pub. L. 100–473, § 2102 Stat. 2299Pub. L. 109–58, title XII119 Stat. 980(, pt. II, § 206, as added , title II, § 213, ; amended , , ; , §§ 1285, 1286, 1295(b), , , 981, 985.)
Editorial Notes
References in Text
act Aug. 26, 1935, ch. 68749 Stat. 803Pub. L. 109–58, title XII, § 1263119 Stat. 974The Public Utility Holding Company Act of 1935, referred to in subsec. (c), is title I of , , which was classified generally to chapter 2C (§ 79 et seq.) of Title 15, Commerce and Trade, prior to repeal by , , . For complete classification of this Act to the Code, see Tables.
Amendments
Pub. L. 109–58, § 1295(b)(1)2005—Subsec. (a). , substituted “hearing held” for “hearing had” in first sentence.
Pub. L. 109–58, § 1295(b)(2)Subsec. (b). , struck out “the public utility to make” before “refunds of any amounts paid” in seventh sentence.
Pub. L. 109–58, § 1285, in second sentence, substituted “the date of the filing of such complaint nor later than 5 months after the filing of such complaint” for “the date 60 days after the filing of such complaint nor later than 5 months after the expiration of such 60-day period”, in third sentence, substituted “the date of the publication” for “the date 60 days after the publication” and “5 months after the publication date” for “5 months after the expiration of such 60-day period”, and in fifth sentence, substituted “If no final decision is rendered by the conclusion of the 180-day period commencing upon initiation of a proceeding pursuant to this section, the Commission shall state the reasons why it has failed to do so and shall state its best estimate as to when it reasonably expects to make such decision” for “If no final decision is rendered by the refund effective date or by the conclusion of the 180-day period commencing upon initiation of a proceeding pursuant to this section, whichever is earlier, the Commission shall state the reasons why it has failed to do so and shall state its best estimate as to when it reasonably expects to make such decision”.
Pub. L. 109–58, § 1286Subsec. (e). , added subsec. (e).
Pub. L. 100–473, § 2(1)1988—Subsec. (a). , inserted provisions for a statement of reasons for listed changes, hearings, and specification of issues.
Pub. L. 100–473, § 2(2)Subsecs. (b) to (d). , added subsecs. (b) and (c) and redesignated former subsec. (b) as (d).
Statutory Notes and Related Subsidiaries
Effective Date of 1988 Amendment
Pub. L. 100–473, § 4102 Stat. 2300
Limitation on Authority Provided
Pub. L. 100–473, § 3102 Stat. 2300
Study
Pub. L. 100–473, § 5102 Stat. 2301, , , directed that, no earlier than three years and no later than four years after , Federal Energy Regulatory Commission perform a study of effect of amendments to this section, analyzing (1) impact, if any, of such amendments on cost of capital paid by public utilities, (2) any change in average time taken to resolve proceedings under this section, and (3) such other matters as Commission may deem appropriate in public interest, with study to be sent to Committee on Energy and Natural Resources of Senate and Committee on Energy and Commerce of House of Representatives.